The Schedule Performance Index (SPI) is calculated as:
Select your answer
A
Earned Value ÷ Planned Value
B
Actual Cost ÷ Earned Value
C
Planned Value ÷ Budgeted Cost
D
Earned Value ÷ Actual Cost