BCM - Bachelor of Construction Management Practice Test
BCM - Bachelor of Construction Management BCM Construction Law and Contracts 2
A Notice to Proceed (NTP) in construction contracts signals:
Select your answer
A
The official authorization for the contractor to begin work on a specific date
B
Completion of the design phase
C
Approval of the contractor's schedule by the owner
D
Issuance of the certificate of substantial completion
Hint