Strategy and Plan Development Flashcards

7 cards from real BCM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Strategy and Plan Development flashcards as text
  1. When selecting a continuity strategy, which factor MOST directly determines whether a hot site is justified over a warm site?

    Answer: Maximum Tolerable Downtime (MTD) for critical functions

    MTD defines how long operations can be down before unacceptable consequences occur, directly dictating the required recovery speed and thus site readiness level.

  2. A BCP strategy that relies on a third-party vendor to supply emergency resources is BEST described as:

    Answer: Outsourcing strategy

    An outsourcing strategy delegates recovery capabilities to an external provider under a contractual service arrangement.

  3. Which document translates broad BCM strategies into specific, step-by-step operational instructions for staff?

    Answer: Business Continuity Plan

    The Business Continuity Plan contains detailed procedures that operationalize recovery strategies for personnel during an incident.

  4. A company identifies that losing its customer database for more than 4 hours would be catastrophic. This threshold is known as the:

    Answer: Maximum Tolerable Downtime (MTD)

    MTD (also called Maximum Tolerable Period of Disruption) is the longest period an organization can survive without a critical function before consequences become unacceptable.

  5. During strategy selection, 'do nothing' is occasionally a valid option when:

    Answer: The cost of mitigation exceeds the potential impact of the risk

    When the cost of implementing a continuity strategy outweighs the financial and operational impact of the risk, accepting the risk (do nothing) may be a rational decision.

  6. Which element is MOST critical when developing a work area recovery strategy for a loss-of-building scenario?

    Answer: Availability of sufficient workspace with necessary technology

    Staff must have the physical workspace and technology tools needed to perform critical functions at the alternate location.

  7. A financial services firm maintains a fully operational duplicate data center that mirrors its primary center in real time. This strategy is called:

    Answer: Hot standby

    A hot standby (hot site) is a fully equipped, operational duplicate facility that can take over immediately with minimal or zero data loss.