โ† All BCM Flashcard Decks

Construction Cost Estimating and Control Flashcards

6 cards from real BCM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 Construction Cost Estimating and Control flashcards as text
  1. Job cost accounting in construction differs from standard accounting because it tracks costs:

    Answer: By individual project and work activity rather than by time period alone

    Job cost accounting captures all costs attributable to specific projects and work items, enabling project-level profitability analysis.

  2. The purpose of a bid bond in the construction bidding process is to:

    Answer: Guarantee that the low bidder will enter into the contract and provide required bonds

    A bid bond protects the owner from a bidder who wins but refuses to sign the contract, covering the difference between the low bid and the next acceptable bid.

  3. Life-cycle cost analysis in construction evaluates:

    Answer: Total cost of ownership including initial construction, operation, maintenance, and eventual replacement

    Life-cycle cost analysis considers all costs over a building's entire lifespan, often favoring higher first-cost options that save money in operation and maintenance.

  4. Preliminary budget estimates prepared during the schematic design phase are typically based on:

    Answer: Gross area multiplied by historical cost-per-square-foot benchmarks for similar project types

    At schematic design, limited detail forces estimators to rely on area-based parametric benchmarks rather than detailed quantity takeoffs.

  5. Which pricing strategy in construction bidding involves adding a fixed percentage markup to all direct costs?

    Answer: Cost-plus-percentage markup

    Cost-plus-percentage pricing adds a set percentage over actual costs for overhead and profit, though it may reduce incentive for cost efficiency.

  6. In construction purchasing, the phrase 'buy-out' refers to:

    Answer: Awarding subcontracts and material purchases after the main contract is signed

    Buy-out is the process of negotiating and awarding all subcontracts and major material orders to lock in actual costs after the GC is under contract.