When disassembling a reduced pressure zone (RPZ) assembly for maintenance, what is the correct first step?
-
A
Shut off downstream isolation valve only
-
B
Relieve pressure by opening test cocks before closing isolation valves
-
C
Remove the relief valve before closing any valves
-
D
Close both isolation valves simultaneously before opening any test cocks