What does a risk register primarily document during a building assessment project?
-
A
Cost estimates for all proposed improvements
-
B
Identified risks, their likelihood, impact, and planned responses
-
C
Contractor license numbers and insurance certificates
-
D
Utility billing history for the past 12 months