AWWA Project Planning and Management 2 — Questions and Answers
Question 1: Which scheduling technique uses probability distributions to account for uncertainty in task durations?
- Critical Path Method (CPM)
- Program Evaluation and Review Technique (PERT) (Correct answer)
- Gantt Chart
- Work Breakdown Structure (WBS)
Correct answer: Program Evaluation and Review Technique (PERT)
PERT uses three-point estimates (optimistic, most likely, pessimistic) to model uncertainty in task durations.
Question 2: In water utility project management, what does a 'lessons learned' document primarily serve to accomplish?
- Assign blame for project delays
- Improve processes on future projects by capturing knowledge (Correct answer)
- Satisfy regulatory audit requirements only
- Document contractor performance for litigation
Correct answer: Improve processes on future projects by capturing knowledge
Lessons learned documents capture successes and failures to improve planning and execution of future projects.
Question 3: A water treatment plant expansion is 60% complete but has spent 75% of its budget. What does this indicate?
- The project is on schedule and under budget
- The project is over budget relative to work completed (Correct answer)
- The project scope has been reduced
- The contractor is performing efficiently
Correct answer: The project is over budget relative to work completed
Spending 75% of budget for only 60% completion means the cost performance index (CPI) is less than 1, indicating a cost overrun.
Question 4: Which document formally authorizes a water utility project and identifies the project manager's authority?
- Project scope statement
- Project charter (Correct answer)
- Statement of work
- Procurement plan
Correct answer: Project charter
The project charter formally authorizes the project and grants the project manager authority to apply resources.
Question 5: When managing a pipeline replacement project, what is the primary purpose of a risk register?
- Track contractor invoices
- Document identified risks, their probability, impact, and response strategies (Correct answer)
- List all project stakeholders
- Record daily construction progress
Correct answer: Document identified risks, their probability, impact, and response strategies
A risk register is a living document that catalogs project risks along with their likelihood, potential impact, and planned responses.
Question 6: In earned value management (EVM), what does the Schedule Performance Index (SPI) greater than 1.0 indicate?
- The project is over budget
- The project is ahead of schedule (Correct answer)
- The project is behind schedule
- The project scope has increased
Correct answer: The project is ahead of schedule
An SPI greater than 1.0 means the project is earning more value than planned, indicating it is ahead of schedule.
Question 7: Which type of contract places the greatest financial risk on the contractor for a water infrastructure project?
- Cost-plus-fixed-fee
- Time and materials
- Firm fixed price (lump sum) (Correct answer)
- Cost-plus-incentive-fee
Correct answer: Firm fixed price (lump sum)
In a firm fixed price contract, the contractor bears all cost risk since the price does not change regardless of actual costs incurred.
Which scheduling technique uses probability distributions to account for uncertainty in task durations?