Under OSHA's PSM standard (29 CFR 1910.119), which element requires a documented review of process technology, equipment, and procedures when a change is made to a covered process?
-
A
Process Hazard Analysis (PHA)
-
B
Pre-Startup Safety Review (PSSR)
-
C
Management of Change (MOC)
-
D
Mechanical Integrity (MI)