A Preliminary Hazard Analysis (PHA) is most appropriately conducted:
-
A
Early in the conceptual or design phase, before detailed designs are finalized
-
B
After a serious incident has occurred to identify root causes
-
C
During final product testing before release to market
-
D
As an annual review of existing hazard control measures