Project Management Flashcards

7 cards from real ASHRAE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Management flashcards as text
  1. In a Critical Path Method (CPM) schedule, which statement best describes the critical path?

    Answer: The longest path through the network, usually with zero total float

    The critical path is the longest-duration sequence and sets the project finish date, so its activities typically have zero float.

  2. Total float for an activity is best defined as:

    Answer: The time the activity can be delayed without delaying project completion

    Total float is how long an activity can slip without moving the project's finish date.

  3. A project manager overlaps ductwork installation with the final phase of structural steel to recover schedule. What is this technique called?

    Answer: Fast-tracking

    Fast-tracking runs activities in parallel that would normally be sequential, which raises the risk of rework.

  4. Adding a second shift of pipefitters at extra cost to shorten a critical activity is an example of:

    Answer: Crashing

    Crashing shortens duration by adding resources, usually at extra cost.

  5. In a finish-to-start (FS) relationship, what must happen before the successor activity can begin?

    Answer: The predecessor must finish

    Finish-to-start, the most common dependency, requires the predecessor to finish before the successor starts.

  6. What duration does a schedule milestone such as 'Substantial Completion' typically have?

    Answer: Zero duration

    Milestones mark significant points in time and have zero duration.

  7. Which scheduling technique adjusts start dates to smooth out peaks in crew demand, possibly extending the schedule?

    Answer: Resource leveling

    Resource leveling reschedules activities to resolve over-allocation and can lengthen the critical path.