In a Critical Path Method (CPM) schedule, which statement best describes the critical path?
Answer: The longest path through the network, usually with zero total float
The critical path is the longest-duration sequence and sets the project finish date, so its activities typically have zero float.
Total float for an activity is best defined as:
Answer: The time the activity can be delayed without delaying project completion
Total float is how long an activity can slip without moving the project's finish date.
A project manager overlaps ductwork installation with the final phase of structural steel to recover schedule. What is this technique called?
Answer: Fast-tracking
Fast-tracking runs activities in parallel that would normally be sequential, which raises the risk of rework.
Adding a second shift of pipefitters at extra cost to shorten a critical activity is an example of:
Answer: Crashing
Crashing shortens duration by adding resources, usually at extra cost.
In a finish-to-start (FS) relationship, what must happen before the successor activity can begin?
Answer: The predecessor must finish
Finish-to-start, the most common dependency, requires the predecessor to finish before the successor starts.
What duration does a schedule milestone such as 'Substantial Completion' typically have?
Answer: Zero duration
Milestones mark significant points in time and have zero duration.
Which scheduling technique adjusts start dates to smooth out peaks in crew demand, possibly extending the schedule?
Answer: Resource leveling
Resource leveling reschedules activities to resolve over-allocation and can lengthen the critical path.