ASEP Technical Reviews and Audits 1 — Questions and Answers
Question 1: What is the primary purpose of a System Requirements Review (SRR)?
- To confirm the system design is complete and ready for production
- To evaluate the completeness, consistency, and adequacy of system requirements (Correct answer)
- To verify the system has been built as designed and meets performance targets
- To assess manufacturing and production readiness before fabrication begins
Correct answer: To evaluate the completeness, consistency, and adequacy of system requirements
The SRR evaluates whether system requirements are complete, consistent, and adequate to proceed into preliminary design.
Question 2: Which formal technical review is conducted to assess the maturity of the preliminary design before transitioning to detailed design?
- System Requirements Review (SRR)
- Critical Design Review (CDR)
- Preliminary Design Review (PDR) (Correct answer)
- Production Readiness Review (PRR)
Correct answer: Preliminary Design Review (PDR)
The PDR is specifically conducted to assess the preliminary design's maturity and authorize transition to detailed design activities.
Question 3: The Critical Design Review (CDR) is conducted to confirm that:
- All system-level requirements have been baselined and approved by the customer
- All integration and testing activities have been completed satisfactorily
- The detailed design is sufficiently mature to proceed to fabrication and testing (Correct answer)
- The system has been fully integrated with all external interface systems
Correct answer: The detailed design is sufficiently mature to proceed to fabrication and testing
CDR confirms that the detailed design is mature enough to authorize the transition to fabrication, demonstration, and test activities.
Question 4: What does the Functional Configuration Audit (FCA) primarily verify?
- That the system's actual functional and performance requirements have been demonstrated and met (Correct answer)
- That the as-built physical product matches the approved product baseline documentation
- That all configuration items are properly documented in the configuration management system
- That the design is ready to enter formal developmental testing activities
Correct answer: That the system's actual functional and performance requirements have been demonstrated and met
The FCA verifies that the system's actual performance has been demonstrated to meet its functional and performance requirements as documented in specifications.
Question 5: Which document serves as the primary input artifact for a System Requirements Review (SRR)?
- Test and Evaluation Master Plan (TEMP)
- Interface Control Document (ICD)
- Product Breakdown Structure (PBS)
- System Specification or System Requirements Document (SRD) (Correct answer)
Correct answer: System Specification or System Requirements Document (SRD)
The System Requirements Document (SRD) or System Specification is the primary artifact evaluated at an SRR to validate requirements completeness and consistency.
Question 6: The primary objective of a Test Readiness Review (TRR) is to:
- Verify that all test results meet the defined acceptance criteria for delivery
- Ensure that testing prerequisites, test procedures, and resources are in place before testing begins (Correct answer)
- Review the overall test strategy and test approach early in the program lifecycle
- Confirm the system design is complete and the product is ready for production
Correct answer: Ensure that testing prerequisites, test procedures, and resources are in place before testing begins
The TRR confirms that all prerequisites, test procedures, facilities, personnel, and support equipment are in place before testing commences.
Question 7: Who typically chairs a formal technical review in a systems engineering program?
- The program customer or contracting officer representative
- The project manager responsible for cost and schedule
- An independent third-party auditor from outside the program
- The chief systems engineer or lead engineer for the program (Correct answer)
Correct answer: The chief systems engineer or lead engineer for the program
The chief systems engineer or lead engineer typically chairs formal technical reviews to provide the necessary technical authority and engineering leadership.
What is the primary purpose of a System Requirements Review (SRR)?