Technical Reviews and Audits Flashcards
7 cards from real ASEP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Technical Reviews and Audits flashcards as text
What is the primary purpose of a System Requirements Review (SRR)?
Answer: To evaluate the completeness, consistency, and adequacy of system requirements
The SRR evaluates whether system requirements are complete, consistent, and adequate to proceed into preliminary design.
Which formal technical review is conducted to assess the maturity of the preliminary design before transitioning to detailed design?
Answer: Preliminary Design Review (PDR)
The PDR is specifically conducted to assess the preliminary design's maturity and authorize transition to detailed design activities.
The Critical Design Review (CDR) is conducted to confirm that:
Answer: The detailed design is sufficiently mature to proceed to fabrication and testing
CDR confirms that the detailed design is mature enough to authorize the transition to fabrication, demonstration, and test activities.
What does the Functional Configuration Audit (FCA) primarily verify?
Answer: That the system's actual functional and performance requirements have been demonstrated and met
The FCA verifies that the system's actual performance has been demonstrated to meet its functional and performance requirements as documented in specifications.
Which document serves as the primary input artifact for a System Requirements Review (SRR)?
Answer: System Specification or System Requirements Document (SRD)
The System Requirements Document (SRD) or System Specification is the primary artifact evaluated at an SRR to validate requirements completeness and consistency.
The primary objective of a Test Readiness Review (TRR) is to:
Answer: Ensure that testing prerequisites, test procedures, and resources are in place before testing begins
The TRR confirms that all prerequisites, test procedures, facilities, personnel, and support equipment are in place before testing commences.
Who typically chairs a formal technical review in a systems engineering program?
Answer: The chief systems engineer or lead engineer for the program
The chief systems engineer or lead engineer typically chairs formal technical reviews to provide the necessary technical authority and engineering leadership.