Read the first 7 Technical Specifications flashcards as text
In CSI MasterFormat (2004 and later), which division covers earthwork such as excavation, fill, and site clearing?
Answer: Division 31
Division 31 Earthwork covers site clearing, excavation, fill, grading, and earth stabilization.
A specification section for cast-in-place concrete would be found in which MasterFormat division?
Answer: Division 03
Division 03 Concrete includes formwork, reinforcement, and cast-in-place concrete.
Water distribution piping, sanitary sewers, and storm drainage utilities are specified in which MasterFormat division?
Answer: Division 33
Division 33 Utilities covers site water, sewer, storm drainage, and other utility systems.
Which MasterFormat division contains General Requirements such as submittal procedures, quality control, and temporary facilities?
Answer: Division 01
Division 01 General Requirements governs administrative and procedural requirements applying to all technical sections.
Structural steel framing and steel joists are specified under which MasterFormat division?
Answer: Division 05
Division 05 Metals includes structural steel framing, joists, decking, and metal fabrications.
Asphalt paving, curbs, and site fencing are specified in which MasterFormat division?
Answer: Division 32
Division 32 Exterior Improvements covers paving, curbs, fencing, and planting.
Railway track construction and traffic signaling would most likely appear in which MasterFormat division?
Answer: Division 34
Division 34 Transportation covers rail, guideways, and transportation signaling and control.