Project Management Flashcards

7 cards from real ASCE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Management flashcards as text
  1. A project's BAC is $2,000,000 and the CPI is 0.80. Assuming current cost performance continues, what is the Estimate at Completion (EAC)?

    Answer: $2,500,000

    EAC = BAC / CPI = 2,000,000 / 0.80 = $2,500,000.

  2. Fast-tracking a construction schedule involves:

    Answer: Performing activities in parallel that were originally planned in sequence

    Fast-tracking overlaps sequential activities, which typically increases risk of rework.

  3. When crashing a schedule, which activity should be crashed first?

    Answer: The critical activity with the lowest crash cost per day

    Crashing the cheapest-per-day critical activity shortens the project at minimum added cost.

  4. A Responsibility Assignment Matrix (RACI) identifies which role for each task?

    Answer: Responsible, Accountable, Consulted, Informed

    RACI clarifies who does the work, who owns the outcome, who gives input, and who is kept informed.

  5. Under AIA and EJCDC standard general conditions, a change order differs from a construction change directive mainly because a change order:

    Answer: Is signed by owner and contractor agreeing on price and time adjustments

    A change order reflects mutual agreement, while a directive orders work before price and time are agreed.

  6. In a precedence diagram, a start-to-start relationship with a 3-day lag means:

    Answer: The successor cannot start until 3 days after the predecessor starts

    SS with lag ties the successor's start to the predecessor's start plus the lag.

  7. Which document formally authorizes a project and gives the project manager authority to apply organizational resources?

    Answer: Project charter

    The project charter formally authorizes the project and names the project manager.