โ† All ASCE Flashcard Decks

Project Management Flashcards

7 cards from real ASCE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Management flashcards as text
  1. In Earned Value Management, a project has EV = $450,000 and AC = $500,000. What is the Cost Performance Index (CPI)?

    Answer: 0.90

    CPI = EV / AC = 450,000 / 500,000 = 0.90, meaning the project is over budget.

  2. A bridge rehabilitation project has PV = $1.2M and EV = $1.08M at the status date. What is the Schedule Variance (SV)?

    Answer: -$120,000

    SV = EV - PV = 1.08M - 1.2M = -$120,000, indicating the work is behind schedule.

  3. On a critical path network, an activity has ES = 10, EF = 15, LS = 14, and LF = 19. What is its total float?

    Answer: 4 days

    Total float = LS - ES = 14 - 10 = 4 days (or LF - EF = 19 - 15).

  4. Which contract type places the greatest cost risk on the contractor?

    Answer: Firm fixed-price (lump sum)

    Under a lump-sum contract, the contractor absorbs any overruns beyond the agreed price.

  5. Free float of an activity is best defined as the amount of time it can be delayed without delaying:

    Answer: The early start of any immediately following activity

    Free float protects the early start of successors, while total float protects the project finish.

  6. In a PERT estimate, an activity has optimistic = 4 days, most likely = 7 days, and pessimistic = 16 days. What is the expected duration?

    Answer: 8.0 days

    Te = (O + 4M + P) / 6 = (4 + 28 + 16) / 6 = 8.0 days.

  7. Which delivery method gives a single entity contractual responsibility for both design and construction?

    Answer: Design-build

    Design-build combines designer and builder under one contract with the owner.