ASCE Construction Engineering and Management Flashcards
6 cards from real ASCE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 ASCE Construction Engineering and Management flashcards as text
What is the primary function of a submittal in the construction process?
Answer: To verify that materials/equipment conform to contract requirements
Submittals—such as shop drawings and product data—are reviewed to confirm that proposed materials and methods meet the contract specifications.
In construction scheduling, what is 'float' (or slack)?
Answer: The amount of time an activity can be delayed without delaying the project
Float is the scheduling flexibility available for a non-critical activity before it impacts the overall project completion date.
Which method of construction cost estimating is most detailed and accurate?
Answer: Unit price (quantity takeoff) estimate
A unit price estimate, built from a detailed quantity takeoff multiplied by unit costs, is the most precise estimating method.
What is the purpose of a Notice to Proceed (NTP) in construction contracts?
Answer: To officially authorize the contractor to begin work
The NTP is an official written notice from the owner authorizing the contractor to mobilize and start construction.
Which type of construction delivery method has the owner contracting separately with a designer and a contractor?
Answer: Design-Bid-Build
In Design-Bid-Build, the owner holds separate contracts with the architect/engineer and the general contractor in a sequential process.
What does a cost performance index (CPI) of 1.2 indicate?
Answer: The project is getting $1.20 of value for every $1.00 spent
A CPI greater than 1.0 means the project is under budget, earning more value than the money being spent.