Question 1: Water distribution piping, sanitary sewers, and storm drainage utilities are specified in which MasterFormat division?
- Division 22
- Division 34
- Division 33 (Correct answer)
- Division 32
Correct answer: Division 33
Division 33 Utilities covers site water, sewer, storm drainage, and other utility systems.
Question 2: Which tensile test result is most commonly used as a measure of a steel's ductility?
- Modulus of elasticity
- Yield strength
- Percent elongation at fracture (Correct answer)
- Ultimate tensile strength
Correct answer: Percent elongation at fracture
Percent elongation over a gauge length shows how much plastic deformation the steel can take before it fractures.
Question 3: When crashing a schedule, which activity should be crashed first?
- The critical activity with the lowest crash cost per day (Correct answer)
- The critical activity with the highest crash cost per day
- The non-critical activity with the lowest crash cost
- The longest activity in the network
Correct answer: The critical activity with the lowest crash cost per day
Crashing the cheapest-per-day critical activity shortens the project at minimum added cost.
Question 4: A specification that names one manufacturer's product and allows alternatives through an 'or equal' clause is best described as:
- Closed proprietary
- Performance
- Open proprietary (Correct answer)
- Descriptive
Correct answer: Open proprietary
An open proprietary specification names products but permits equivalent substitutes.
Question 5: On a statistical process control chart, a single test result plotted above the upper control limit most likely indicates:
- That the control limits are too wide
- Normal common-cause variation
- A special (assignable) cause of variation (Correct answer)
- That the process is fully capable
Correct answer: A special (assignable) cause of variation
Points outside the control limits signal special-cause variation that should be investigated.
Question 6: A process operating at a Six Sigma level, allowing for the conventional 1.5-sigma shift, produces approximately how many defects per million opportunities?
- 6,210
- 233
- 66
- 3.4 (Correct answer)
Correct answer: 3.4
Six Sigma with the 1.5σ shift equates to about 3.4 DPMO.
Question 7: Which of the following best describes specific energy in open channel flow?
- Energy per unit weight measured with respect to the channel bottom as datum (Correct answer)
- The sum of pressure head and velocity head only
- Total energy measured above a datum at the channel bed
- Energy dissipated per unit length of channel
Correct answer: Energy per unit weight measured with respect to the channel bottom as datum
Specific energy (E = y + V²/2g) is the total energy per unit weight of fluid measured with respect to the channel bottom, combining depth (pressure term) and velocity head.
Question 8: Fast-tracking a construction schedule involves:
- Adding resources to critical activities to shorten them
- Removing scope from the project
- Performing activities in parallel that were originally planned in sequence (Correct answer)
- Extending the contract completion date
Correct answer: Performing activities in parallel that were originally planned in sequence
Fast-tracking overlaps sequential activities, which typically increases risk of rework.
Question 9: What is the primary function of public transportation systems?
- Increase private car ownership.
- Provide efficient mobility and reduce congestion. (Correct answer)
- Expand suburban housing developments.
- Encourage long-distance commuting.
Correct answer: Provide efficient mobility and reduce congestion.
Public transportation systems, such as buses, trains, and subways, primarily function to provide efficient and accessible mobility for a large number of people. By offering an alternative to private vehicles, they help reduce traffic congestion, lower carbon emissions, and decrease the demand for parking. This enhances urban livability, supports economic development, and promotes more sustainable travel patterns.
Question 10: Which type of bridge is best suited for spanning long distances with minimal supports?
- Suspension bridge (Correct answer)
- Truss bridge
- Beam bridge
- Arch bridge
Correct answer: Suspension bridge
Suspension bridges are ideal for spanning long distances because their design efficiently distributes weight. The main cables, anchored at each end, carry the load from the deck via vertical suspender cables, transferring tension to the towers and then to the anchorages. This allows for very long main spans with fewer intermediate supports compared to other bridge types, making them suitable for vast crossings.
Question 11: A bridge rehabilitation project has PV = $1.2M and EV = $1.08M at the status date. What is the Schedule Variance (SV)?
- +$120,000
- -$120,000 (Correct answer)
- -$1,080,000
- +$1,080,000
Correct answer: -$120,000
SV = EV - PV = 1.08M - 1.2M = -$120,000, indicating the work is behind schedule.
Question 12: Under ACI 318, what strength reduction factor (φ) applies to tension-controlled flexural sections?
- 0.90 (Correct answer)
- 0.75
- 0.65
- 0.85
Correct answer: 0.90
ACI 318 assigns φ = 0.90 to tension-controlled sections because they fail in a ductile way.
Question 13: Which ASTM test method measures the air content of normal-weight fresh concrete using the pressure method?
- ASTM C173
- ASTM C138
- ASTM C231 (Correct answer)
- ASTM C1064
Correct answer: ASTM C231
ASTM C231 is the pressure method, while C173 is the volumetric method used for lightweight concrete.
Question 14: On a critical path network, an activity has ES = 10, EF = 15, LS = 14, and LF = 19. What is its total float?
- 9 days
- 5 days
- 0 days
- 4 days (Correct answer)
Correct answer: 4 days
Total float = LS - ES = 14 - 10 = 4 days (or LF - EF = 19 - 15).
Question 15: What is the effective throat of an equal-leg fillet weld with leg size w?
- 1.414w
- 0.5w
- 0.707w (Correct answer)
- w
Correct answer: 0.707w
For a 45° fillet weld, the throat is w·sin45° ≈ 0.707w.
Question 16: Before a concrete pour, a special inspector checks reinforcement. Which item is LEAST likely to be part of that inspection?
- Bar size and spacing
- Lap splice lengths
- Concrete cover and support chairs
- Concrete slump (Correct answer)
Correct answer: Concrete slump
Slump is a fresh-concrete test done during placement, not part of the pre-pour reinforcing inspection.
Question 17: What modulus of elasticity is typically used for structural steel in U.S. design practice?
- 10,000 ksi
- 45,000 ksi
- 29,000 ksi (Correct answer)
- 3,600 ksi
Correct answer: 29,000 ksi
AISC specifies E = 29,000 ksi for structural steel regardless of grade.
Question 18: How should engineering changes to testing methods be managed?
- Verbal approval is sufficient
- Changes can be made at the engineer's discretion
- By email notification after implementation
- Through a formal change control process with documentation and approval (Correct answer)
Correct answer: Through a formal change control process with documentation and approval
Formal change control processes ensure all modifications are properly evaluated, approved, documented, and communicated.
Question 19: A soil has a liquid limit of 48 and a plastic limit of 22. What is its plasticity index?
- 70
- 35
- 26 (Correct answer)
- 22
Correct answer: 26
Plasticity index equals liquid limit minus plastic limit: 48 - 22 = 26.
Question 20: Which analysis method is essential for testing methods?
- Guessing based on experience alone
- Copying previous project specifications without review
- Visual inspection only
- Quantitative analysis using validated engineering methods and calculations (Correct answer)
Correct answer: Quantitative analysis using validated engineering methods and calculations
Validated engineering methods and calculations provide the quantitative basis needed for sound engineering decisions.
Question 21: How should engineering changes to project management be managed?
- Through a formal change control process with documentation and approval (Correct answer)
- Changes can be made at the engineer's discretion
- Verbal approval is sufficient
- By email notification after implementation
Correct answer: Through a formal change control process with documentation and approval
Formal change control processes ensure all modifications are properly evaluated, approved, documented, and communicated.
Question 22: Portland cement types (I, II, III, V, etc.) are defined by which standard?
- ASTM C618
- ASTM C150 (Correct answer)
- ASTM C94
- ASTM C33
Correct answer: ASTM C150
ASTM C150 is the standard specification for portland cement.
Question 23: What is the main factor influencing soil bearing capacity?
- Depth of water table
- Soil type (Correct answer)
- Amount of vegetation
- Wind speed
Correct answer: Soil type
Soil type is the main factor influencing soil bearing capacity because different soil compositions have varying strengths and compressibilities. Cohesive soils like clay behave differently from granular soils like sand, affecting how much load they can safely support before shear failure or excessive settlement occurs. Engineers must analyze the specific soil type to determine appropriate foundation designs and ensure structural stability.
Question 24: How is the yield strength of a metal with no clear yield point, such as high-strength steel or aluminum, usually determined?
- By the 0.2% offset method (Correct answer)
- From the ultimate strength divided by 1.5
- From the fracture stress
- From the proportional limit by eye
Correct answer: By the 0.2% offset method
Draw a line parallel to the elastic slope, offset by 0.002 strain; the stress where it crosses the curve is the yield strength.
Question 25: The slump test (ASTM C143) is mainly used to measure which property of fresh concrete?
- Workability/consistency (Correct answer)
- Setting time
- Compressive strength
- Air content
Correct answer: Workability/consistency
Slump measures the consistency, or workability, of fresh concrete.
Question 26: Per ACI 318, what strength reduction factor φ applies to flexure in a tension-controlled reinforced concrete section?
- 0.75
- 0.90 (Correct answer)
- 0.65
- 0.85
Correct answer: 0.90
Tension-controlled sections are ductile and receive φ = 0.90.
Question 27: What does a cost performance index (CPI) of 1.2 indicate?
- The project is getting $1.20 of value for every $1.00 spent (Correct answer)
- The project is 20% behind schedule
- The project is spending 20% more than planned
- The project is 20% over budget
Correct answer: The project is getting $1.20 of value for every $1.00 spent
A CPI greater than 1.0 means the project is under budget, earning more value than the money being spent.
Question 28: Under NEPA, if an Environmental Assessment finds no significant impacts, the federal agency issues a:
- Finding of No Significant Impact (Correct answer)
- Notice of Intent
- Categorical Exclusion
- Record of Decision
Correct answer: Finding of No Significant Impact
An EA that finds no significant impact ends with a FONSI instead of an EIS.
Question 29: A project's BAC is $2,000,000 and the CPI is 0.80. Assuming current cost performance continues, what is the Estimate at Completion (EAC)?
- $1,600,000
- $2,500,000 (Correct answer)
- $2,000,000
- $2,400,000
Correct answer: $2,500,000
EAC = BAC / CPI = 2,000,000 / 0.80 = $2,500,000.
Question 30: In the Modified Proctor test (ASTM D1557), what hammer weight and drop height are used?
- 10 lb hammer, 18 in drop (Correct answer)
- 5.5 lb hammer, 18 in drop
- 5.5 lb hammer, 12 in drop
- 10 lb hammer, 12 in drop
Correct answer: 10 lb hammer, 18 in drop
Modified Proctor uses a 10 lb hammer dropped 18 in, delivering much more compactive energy than Standard Proctor (5.5 lb, 12 in).
Question 31: Installation tolerances and field quality control testing are typically placed in which part of a section?
- Part 1 General
- Part 3 Execution (Correct answer)
- Part 2 Products
- The supplementary conditions
Correct answer: Part 3 Execution
Part 3 Execution covers preparation, installation, tolerances, and field quality control.
Question 32: Deformed and plain carbon-steel bars for concrete reinforcement are commonly specified to:
- ASTM A615 (Correct answer)
- ASTM A992
- ASTM A36
- ASTM A325
Correct answer: ASTM A615
ASTM A615 covers deformed and plain carbon-steel bars for concrete reinforcement.
Question 33: For a strip footing on saturated clay under undrained (φ = 0) conditions, the Prandtl/Meyerhof bearing capacity factor Nc is:
- 5.70
- 3.14
- 1.00
- 5.14 (Correct answer)
Correct answer: 5.14
Nc = π + 2 ≈ 5.14 for φ = 0; Terzaghi's original value is 5.7.
Question 34: Under IBC Chapter 17, the Statement of Special Inspections is normally prepared by:
- The general contractor
- The concrete supplier
- The registered design professional in responsible charge (Correct answer)
- The building owner's insurer
Correct answer: The registered design professional in responsible charge
IBC requires the registered design professional to prepare the statement of special inspections as part of the permit documents.
Question 35: Per ASTM C143, how long should it take to raise the slump cone vertically after rodding?
- 1 ± 0.5 seconds
- 30 ± 10 seconds
- 15 ± 5 seconds
- 5 ± 2 seconds (Correct answer)
Correct answer: 5 ± 2 seconds
ASTM C143 requires lifting the mold steadily in 5 ± 2 seconds without lateral or torsional motion.
Question 36: Which analysis method is essential for quality assurance?
- Guessing based on experience alone
- Copying previous project specifications without review
- Visual inspection only
- Quantitative analysis using validated engineering methods and calculations (Correct answer)
Correct answer: Quantitative analysis using validated engineering methods and calculations
Validated engineering methods and calculations provide the quantitative basis needed for sound engineering decisions.
Question 37: Which document formally authorizes a project and gives the project manager authority to apply organizational resources?
- Scope statement
- Work breakdown structure
- Project charter (Correct answer)
- Risk register
Correct answer: Project charter
The project charter formally authorizes the project and names the project manager.
Question 38: In Marshall mix design for heavy-traffic pavements, how many blows per side are typically applied to compact specimens?
- 35
- 50
- 100
- 75 (Correct answer)
Correct answer: 75
Heavy traffic Marshall designs use 75 blows per side, while medium and light traffic use 50 and 35.
Question 39: A contractor proposes a different product than specified after award. Who generally bears the burden of proving equivalence?
- The manufacturer of the specified product
- The engineer
- The contractor (Correct answer)
- The owner
Correct answer: The contractor
The party requesting the substitution must demonstrate the proposed product is equal to the specified one.
Question 40: The continuous improvement cycle associated with W. Edwards Deming consists of which four steps?
- Inspect-Test-Accept-Reject
- Design-Build-Verify-Close
- Plan-Do-Check-Act (Correct answer)
- Define-Measure-Analyze-Control
Correct answer: Plan-Do-Check-Act
The Deming (PDCA) cycle is Plan, Do, Check (or Study), Act.
ASCE Civil Engineer, Certified (CE-C)
The CE-C credential is a post-PE, cross-specialty certification validating professional competencies aligned with the Civil Engineering Body of Knowledge (CEBOK), covering technical, professional practice, and leadership domains required for responsible charge in civil engineering.
Exam Rules
- You can skip questions and return to them later
- Flag questions for review before submitting
- No feedback shown until you submit the entire exam
- Unanswered questions count as wrong — answer everything
- 10 pretest questions are mixed in and don't affect your score
- Timer auto-submits when time runs out
- Your progress is auto-saved every 30 seconds