When a client requests a last-minute change to artwork specifications after production has begun, an ART provider should first:
-
A
Begin reworking the piece immediately to avoid conflict
-
B
Document the change request and assess its impact on timeline and cost
-
C
Refuse the change since the contract was already signed
-
D
Delegate the decision to the shipping department