An architect receives an RFI revealing a conflict between the structural and architectural drawings. What is the proper response?
-
A
Issue a written clarification or supplemental instruction resolving the conflict
-
B
Tell the contractor to build whichever is cheaper
-
C
Wait until the punch list to address it
-
D
Instruct the contractor verbally on site