During schematic design, a client requests a major program change that increases the building area by 20%. What should the architect do first?
-
A
Proceed and bill hourly without notification
-
B
Absorb the extra work to maintain the relationship
-
C
Refuse the change until construction documents are complete
-
D
Issue an additional services request per the owner-architect agreement