What does 'substantial completion' mean in construction contract law?
-
A
The point at which the contractor has completed 50% of the work value
-
B
The stage when the work is sufficiently complete for the owner to occupy and use it for its intended purpose
-
C
The date the architect certifies all punch list items are resolved
-
D
The moment the contractor demobilizes from the construction site