A supply planner is analyzing 'pegging' information in the MRP system. What does pegging allow the planner to determine?
-
A
The total on-hand inventory across all warehouse locations
-
B
The specific parent orders or customer demands that created a particular component requirement
-
C
The optimal reorder point for safety stock items
-
D
The supplier's promised delivery dates for open purchase orders