A company notices its S&OP plan is consistently ignored at the operational level. What is the most likely root cause?
-
A
The S&OP plan is not translated into detailed execution plans like MPS and MRP
-
B
The company has too many SKUs to manage
-
C
The demand review is held too infrequently
-
D
Finance is not included in the product review