According to API 510, what must be documented when an owner-user establishes an on-stream inspection interval that exceeds the standard formula-based interval?
-
A
Nothing additional is required
-
B
Documented engineering justification and risk assessment supporting the extended interval
-
C
Only the signature of the plant manager
-
D
A letter from the original equipment manufacturer