You are given a project with a tight deadline and limited resources. Which planning approach is most effective?
-
A
Plan all tasks in the order they come to mind and adjust later
-
B
Identify the critical path — the sequence of dependent tasks that determines overall completion time — and prioritize those
-
C
Focus only on the easiest tasks first to build momentum
-
D
Ask for a deadline extension before starting any work