  1. What is the time-box for the Daily Scrum?

    Answer: 15 minutes

    The Daily Scrum is time-boxed to 15 minutes regardless of Sprint length.

  2. Which artifact represents the long-term objective for the Scrum Team?

    Answer: The Product Goal

    The Product Goal describes a future state of the product and is the long-term target.

  3. When during a Sprint can the Sprint Goal be changed?

    Answer: It remains fixed, though scope may be renegotiated

    The Sprint Goal stays fixed during the Sprint while scope can be clarified with the Product Owner.

  4. Who facilitates ensuring all Scrum events take place and stay within their time-box?

    Answer: The Scrum Master

    The Scrum Master ensures events are held and kept positive and productive within time-boxes.

  5. A new Increment is created when which condition is met?

    Answer: A Product Backlog item meets the Definition of Done

    Each item meeting the Definition of Done adds to the Increment, so multiple can be created per Sprint.

  6. What is the time-box for the Sprint Review in a one-month Sprint?

    Answer: Four hours

    The Sprint Review is time-boxed to a maximum of four hours for a one-month Sprint.

  7. Who is accountable for the Product Backlog's content and availability?

    Answer: The Product Owner

    The Product Owner is accountable for the Product Backlog's content, ordering, and transparency.