Scrum Events and Artifacts Flashcards
7 cards from real Agile Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Scrum Events and Artifacts flashcards as text
What is the maximum time-box for a Sprint Retrospective in a one-month Sprint?
Answer: Three hours
The Sprint Retrospective is time-boxed to a maximum of three hours for a one-month Sprint.
Who is responsible for ordering the items in the Product Backlog?
Answer: The Product Owner
The Product Owner is solely accountable for ordering Product Backlog items to best achieve goals.
During the Daily Scrum, who is required to attend and participate?
Answer: The Developers
The Daily Scrum is an event for the Developers to inspect progress toward the Sprint Goal.
What artifact commitment is associated with the Increment?
Answer: The Definition of Done
The Definition of Done is the commitment that ensures an Increment is usable.
If the team has no useful Definition of Done, what must they do?
Answer: Define one as a minimum, conforming to organization standards
When organizational standards exist the team must follow them as a minimum; otherwise they create their own.
What is the primary purpose of the Sprint Review?
Answer: Inspect the Increment and adapt the Product Backlog
The Sprint Review inspects the outcome of the Sprint and determines future adaptations.
How often can the Product Backlog be refined?
Answer: At any time as an ongoing activity
Product Backlog refinement is an ongoing activity, not a formal Scrum event.