An AEP quality inspector is reviewing a contractor's As-Built drawings at project closeout. What is the inspector's primary concern?
-
A
That the drawings are printed on the correct paper size
-
B
That the drawings accurately reflect all field changes and deviations from the original design
-
C
That the drawings are submitted in alphabetical order
-
D
That the contractor's logo is present on each sheet