Question 1: What does SCADA stand for in substation automation?
- System Control and Data Access
- Supervisory Control and Data Acquisition (Correct answer)
- Substation Control and Distribution Automation
- Smart Circuit and Data Analysis
Correct answer: Supervisory Control and Data Acquisition
SCADA (Supervisory Control and Data Acquisition) systems allow operators to remotely monitor and control substation equipment from a control center.
Question 2: What is the role of a capacitor bank in a distribution substation?
- To store backup power for outages
- To improve power factor and provide voltage support (Correct answer)
- To limit fault currents
- To regulate transformer tap positions
Correct answer: To improve power factor and provide voltage support
Capacitor banks supply reactive power to improve power factor and support voltage levels on the distribution system.
Question 3: What is a substation 'switching order' used for?
- To order replacement equipment for the substation
- To document and authorize a sequence of switching operations (Correct answer)
- To record equipment maintenance history
- To schedule substation inspections
Correct answer: To document and authorize a sequence of switching operations
A switching order is a written document that authorizes and sequences specific switching operations to safely isolate or energize substation equipment.
Question 4: What is the purpose of an automatic recloser installed on a distribution feeder leaving a substation?
- To measure feeder load continuously
- To automatically restore power after a temporary fault (Correct answer)
- To regulate voltage along the feeder
- To balance load between phases
Correct answer: To automatically restore power after a temporary fault
Reclosers automatically interrupt and re-energize a feeder after a temporary fault, restoring service without manual intervention.
Question 5: What is the significance of a substation's short circuit capacity (fault level)?
- The maximum energy the substation can store
- The maximum fault current the substation equipment must withstand (Correct answer)
- The minimum load the substation must maintain
- The transformer's rated continuous capacity
Correct answer: The maximum fault current the substation equipment must withstand
Short circuit capacity determines the maximum fault current that can flow, which equipment must safely interrupt or withstand without damage.
Question 6: Which instrument transformer is used to measure voltage in a high-voltage substation?
- Current transformer (CT)
- Potential transformer (PT) or voltage transformer (VT) (Correct answer)
- Power transformer
- Autotransformer
Correct answer: Potential transformer (PT) or voltage transformer (VT)
Potential transformers (PTs) or voltage transformers (VTs) step down high voltages to safe, standardized levels (typically 120V) for metering and protection.