A CIO wants to align the network refresh project with corporate OKRs. Which leadership approach best ensures this alignment throughout the project lifecycle?
-
A
Delegate all technical decisions to the network team
-
B
Establish cross-functional steering committees with shared KPIs
-
C
Focus solely on technology deliverables and report at project close
-
D
Limit stakeholder involvement until deployment is complete