A Jira project manager notices that a key stakeholder rarely attends sprint reviews. What is the BEST first step to improve their engagement?
-
A
Remove them from the stakeholder list
-
B
Schedule a 1-on-1 to understand their preferred communication style and barriers
-
C
Send daily status emails to keep them informed
-
D
Escalate the issue to senior management