Quality Assurance & Compliance Flashcards

7 cards from real ACP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Quality Assurance & Compliance flashcards as text
  1. A QA lead notices that escaped defects (bugs found in production) are not being tracked back to the sprint they were introduced in. Which Jira practice addresses this?

    Answer: Using 'Fix Version' and 'Affects Version' fields consistently

    'Affects Version' records which release introduced the defect, and 'Fix Version' tracks when it was resolved, enabling escape defect analysis by sprint/release.

  2. Which Confluence template is most appropriate for documenting a QA test plan that satisfies IEEE 829 standard requirements?

    Answer: Test plan template with scope, approach, and schedule sections

    A test plan template with sections for scope, test approach, resources, and schedule aligns with IEEE 829's required test plan components.

  3. In Jira Software, which built-in report shows the stability of a team's velocity over multiple sprints, helping QA plan test capacity?

    Answer: Velocity Chart

    The Velocity Chart displays completed story points per sprint over time, enabling QA leads to forecast testing capacity for future sprints.

  4. A regulated industry team must demonstrate that no code is deployed without a linked change request in Jira Service Management. Which integration pattern enforces this?

    Answer: Bamboo deployment blocked by JSM change approval status via API check

    Bamboo (or another CI/CD tool) can call the JSM REST API to verify a change request is in 'Approved' status before allowing a deployment to proceed.

  5. When conducting a retrospective on QA process failures in Jira, which issue type is most appropriate for capturing improvement actions that need to be tracked to completion?

    Answer: Story or Task

    Retrospective action items are best captured as Stories or Tasks in Jira so they can be estimated, assigned, prioritized, and tracked in the next sprint.

  6. A compliance auditor requests proof that Jira project configurations (workflows, permission schemes) have not changed over the past year. Where is this evidence found?

    Answer: Jira Admin Audit Log

    The Jira Admin Audit Log records all project and system configuration changes with timestamps and the user who made each change.

  7. A QA engineer uses Jira Automation to close all 'Testing' issues automatically when the linked story is marked 'Done.' Which trigger should be used?

    Answer: Issue transitioned trigger on the parent story

    The 'Issue transitioned' trigger fires when a specified issue changes status, allowing automation to act on linked child or related issues accordingly.