What does ACI 306 define as the minimum duration for protecting concrete from freezing after placement in cold weather?
-
A
Until compressive strength reaches 500 psi
-
B
Until compressive strength reaches 3,500 psi
-
C
Until compressive strength reaches at least 500 psi, typically not less than 2 days
-
D
Until the concrete has cured for 28 days