ACAP - Army Cost Analysis Position Practice Test
ACAP Earned Value Management 2
What does a negative Schedule Variance (SV = EV - PV) indicate on a program?
Select your answer
A
The program is under budget
B
The program is ahead of schedule
C
The program is behind schedule
D
The program has exceeded its management reserve
Hint