A company uses activity-based costing. The cost driver for 'machine setups' is number of setups. Total setup costs are £48,000 and there are 160 setups in the period. Product A requires 40 setups. What is the setup cost allocated to Product A?
-
A
£7,200
-
B
£12,000
-
C
£9,600
-
D
£16,000