Which of the following BEST describes the concept of 'progressive elaboration' in agile business analysis?
-
A
Delivering all requirements upfront before any development begins
-
B
Detailing requirements incrementally as more information becomes available throughout the project
-
C
Assigning detailed requirements to the least experienced team member
-
D
Creating a complete product roadmap before the first sprint