In an agile environment, a business analyst discovers mid-sprint that a stakeholder's requirement conflicts with a previously agreed-upon user story. What is the BEST immediate action?
-
A
Pause the sprint and escalate to the project sponsor
-
B
Raise it in the next daily standup and let the team resolve it
-
C
Collaborate with the product owner to assess impact and prioritize resolution in the backlog
-
D
Document the conflict and defer it to the retrospective