8100 Professional Level Exam Risk Assessment and Management 2 — Questions and Answers
Question 1: What is a 'secondary risk' in risk management?
- A new risk introduced by implementing a risk response (Correct answer)
- A risk ranked second in priority after the primary risk
- A risk identified late in the project lifecycle
- A risk affecting secondary stakeholders only
Correct answer: A new risk introduced by implementing a risk response
Secondary risks arise as a direct consequence of a risk response action, and they must be analyzed and managed just like any other identified risk.
Question 2: In risk management, what does 'risk appetite' describe?
- The amount and type of risk an organization is willing to accept in pursuit of its objectives (Correct answer)
- The total monetary value of risks accepted
- The number of risks allowed on a project
- How quickly management wants risks resolved
Correct answer: The amount and type of risk an organization is willing to accept in pursuit of its objectives
Risk appetite reflects organizational culture and strategic direction, guiding decisions about which risks to pursue, tolerate, or avoid.
Question 3: What is a 'contingency reserve' in project risk management?
- Budget or time set aside to address identified risks that may materialize (Correct answer)
- Emergency funds held by the finance department for unrelated use
- A reserve drawn upon only with executive approval
- Overtime budgeted for every project automatically
Correct answer: Budget or time set aside to address identified risks that may materialize
Contingency reserves are planned budget or schedule buffers specifically tied to identified risks, drawn upon if those risks occur.
Question 4: What distinguishes 'qualitative' from 'quantitative' risk analysis?
- Qualitative ranks risks subjectively; quantitative models risk numerically (Correct answer)
- Qualitative is more accurate than quantitative
- Quantitative analysis is faster than qualitative
- They are the same process with different names
Correct answer: Qualitative ranks risks subjectively; quantitative models risk numerically
Qualitative risk analysis prioritizes risks using expert judgment and rating scales, while quantitative analysis uses numerical data and statistical models.
Question 5: What is a 'trigger condition' (risk trigger) in professional risk management?
- An early warning sign indicating that a risk event is about to occur or has occurred (Correct answer)
- The condition that created the risk originally
- Management approval to activate a contingency plan
- The scheduled date for a risk review meeting
Correct answer: An early warning sign indicating that a risk event is about to occur or has occurred
Risk triggers are observable indicators that alert the team to act on a contingency plan before the full impact of the risk materializes.
Question 6: Which risk response strategy is most appropriate when a risk has a low probability and low impact?
- Accept (Correct answer)
- Avoid
- Transfer
- Escalate
Correct answer: Accept
For low-probability, low-impact risks, acceptance is cost-effective since elaborate response planning would consume more resources than the risk is worth.
What is a 'secondary risk' in risk management?