What is the '10% RT' inspection requirement for pipeline girth welds under CAN/CSA Z662 and how are the welds selected?
-
A
10% of all girth welds by a specific welder must be radiographically tested; if defects exceed limits, additional welds by that welder are tested (100% if rejection rate is high)
-
B
The first 10 welds of every day must be radiographed
-
C
10% of each type of fitting connection must be tested by RT
-
D
10% of the linear weld length must be tested; the selection is random