A client requests a mid-project scope change that would require significant rework. What is the professional standard response?
-
A
Refuse the change to protect the original timeline
-
B
Document the change, assess impact, and issue a change order with revised cost and schedule
-
C
Absorb the extra work to maintain client goodwill
-
D
Complete the original scope and then address the change after delivery