FREE Bachelor of Construction Management Trivia Questions and Answers

0%

Any activity's "free float" is defined as the difference between

Correct! Wrong!

The definition of free float for any activity is the difference between its earliest finish time and earliest start time for its successor activity.

Choose the untrue statement from the list below:

Correct! Wrong!

A machine costs Rs. 10,000,00 and is expected to last for 10 years. After ten years, the salvage value is Rs. 150,000. Using the conventional straight line approach of evaluating depreciation, the machine's book value after five years is

Correct! Wrong!

The independent float only impacts

Correct! Wrong!

The independent float, also known as free float, affects only the particular activity involved.

Sheep foot rolling involves the fundamental movement of

Correct! Wrong!

Pick the false statement.

Correct! Wrong!

A phony endeavor.

Correct! Wrong!

A dummy activity in project management is an artificially introduced activity that is used to maintain logical relationships between other activities. It is represented by a dotted line in project network diagrams, such as the arrow diagramming method (ADM) or the precedence diagramming method (PDM). A dummy activity does not consume any time or resources and is solely used for establishing dependencies and sequencing of other activities in the project.