FREE CCIL Concrete Questions and Answers

0%

When casting 150mm x 150mm x 535mm beams, what is the minimum sample size required?

Correct! Wrong!

Explanation:
According to CCIL standards, when casting 150mm x 150mm x 535mm beams, a minimum sample size of 55 liters is required. This volume ensures that there is sufficient concrete available for casting the beams while also accounting for any potential variations in the mix and ensuring accurate test results.

What temperature range is considered stable before mixing concrete?

Correct! Wrong!

Explanation:
According to CCIL standards, the temperature range considered stable before mixing concrete is 23°C with a tolerance of +/- 2°C. It's crucial to maintain stable temperatures to ensure consistency in concrete properties and performance. Deviations from this range could affect the setting time, workability, and overall quality of the concrete mix.

When casting 150mm x 300mm cylinders, what is the minimum sample size required?

Correct! Wrong!

Explanation:
According to CCIL standards, when casting 150mm x 300mm cylinders, a minimum sample size of 30 liters is necessary. This ensures there is enough concrete for proper casting and testing, maintaining the accuracy and reliability of the results.

How much time is typically spent mixing concrete?

Correct! Wrong!

Explanation:
The CCIL recommends a specific mixing procedure for concrete to ensure uniformity and proper hydration of the cementing materials. This involves mixing the concrete for an initial period, allowing it to rest, and then mixing it again for a shorter duration. This sequence helps achieve the desired consistency and ensures that all components are thoroughly blended without overmixing, which can lead to air entrainment and affect the quality of the concrete.

Which of the following best describes the sampling location when retrieving a sample from a mixer/truck agitator for concrete testing?

Correct! Wrong!

Explanation:
When sampling from a mixer/truck agitator for concrete testing, the sample should be taken from between 10% and 90% of the mixture depth to ensure a representative sample. This range helps avoid potential biases from the surface or bottom of the mixture. However, it's important to note that this guideline may not apply when testing with certain additives like Super P.

How many water-to-cementing materials ratios are typically needed for concrete trial mixes?

Correct! Wrong!

Explanation:
CCIL standards typically require three water-to-cementing materials ratios for concrete trial mixes. These trial mixes help determine the optimal ratio that achieves the desired concrete properties such as strength, workability, and durability. Conducting trials with different ratios allows for the selection of the most suitable mix design for the specific construction project.

When casting more than three cylinders/specimens, how much extra sample is needed?

Correct! Wrong!

Explanation:
CCIL recommends adding 10% extra sample volume beyond the volume required for casting the specified number of cylinders/specimens. This additional volume accounts for any potential loss during the casting process and ensures that there is sufficient material available for testing and quality assurance purposes.

When casting 3 cylinders measuring 100mm x 200mm, what is the minimum sample size required?

Correct! Wrong!

Explanation:
According to CCIL standards, when casting 3 cylinders measuring 100mm x 200mm, a minimum sample size of 20 liters is required. This ensures that an adequate amount of concrete is available for proper casting and testing of the cylinders, maintaining the integrity and accuracy of the results.

When sampling plastic concrete, which method is recommended?

Correct! Wrong!

Explanation:
When sampling plastic concrete, CCIL recommends passing a receptacle completely through a discharge stream or diverting a discharge stream completely into a sampling container. This ensures a representative sample is obtained from the flowing concrete, which is crucial for accurate testing and analysis.

What does "Air Content" refer to in concrete testing, according to CCIL?

Correct! Wrong!

Explanation:
According to CCIL standards, the term "Air Content" specifically pertains to the volume of air voids present in plastic concrete, which refers to the concrete before it sets or hardens. This measurement excludes the pore space within the aggregate particles and is determined by observing the change in air volume in concrete when subjected to pressure changes.

Where should cementing materials be stored?

Correct! Wrong!

Explanation:
Cementing materials should be stored in a dry place to prevent moisture absorption, which can lead to clumping and reduced effectiveness. Moisture-proof containers help maintain the quality of the cementing materials by protecting them from humidity and moisture in the air. Proper storage ensures that the cement remains free-flowing and maintains its chemical properties until it is used in concrete production.

Premium Tests $49/mo
FREE November-2024